Sinoma EC Engineering Branch Successfully Obtains PAC Certificate for Saudi Arabia’s First ORC Cement Waste Heat Power Generation Project under EPC Turnkey Contract
Source:Sinoma EC Engineering Branch Date:2026.11.18

Recently, good news came from the cement kiln waste heat power generation project of Riyadh Cement Company in Saudi Arabia, for which Sinoma EC Engineering Branch served as the EPC turnkey contractor: following its first power generation and grid connection on February 4, 2026, the project successively completed stability and performance tests and formally obtained the PAC (Provisional Acceptance Certificate) issued by the owner on November 16, 2026. This marks that the project’s engineering construction and system performance have received authoritative recognition from the owner, and that the project has fully entered a new stage of stable operation and warranty service.

First in Saudi Arabia: ORC Technology Empowers the Green Power Transition of the Cement Industry

This project is Saudi Arabia’s first clean energy cement waste heat power generation project using ORC (Organic Rankine Cycle) technology, with an installed capacity of 14 MW. Sinoma EC Engineering Branch undertook full-process EPC turnkey contracting covering design, procurement, construction, commissioning and performance testing.

Leveraging low-grade waste heat resources from the kiln head and kiln tail of the cement production line, the project efficiently converts them into clean electricity through the ORC power generation system. It is precisely adapted to Saudi Arabia’s high-temperature, arid and high-irradiation operating conditions. While ensuring the continuity of main cement production, it significantly reduces the owner’s electricity costs and carbon emission intensity, making it a typical demonstration of the synergistic utilization of industrial energy conservation and clean energy.

From First Grid Connection to PAC: Full-System Verification Meets Standards

On February 4, 2026, the project completed full-system joint commissioning and achieved its first power generation and grid connection, with the main operating parameters of the unit better than design expectations. Since then, the project team has continued to focus on the following key milestones:

Completed the continuous stability operation test; system load response, thermal control and electrical protection logic were stable and reliable;

Completed the performance test under the contract; key indicators such as power generation, thermal efficiency and waste heat recovery rate met and exceeded the EPC contract requirements;

Completed punch-list closure and operation training, and established a standardized O&M manual to ensure the owner’s independent operation capability.

Jointly confirmed by the owner and the consultant, the PAC was successfully issued on November 16, becoming another high-quality contract performance achievement of Sinoma Energy Conservation in the overseas ORC waste heat power generation field.

Robust Contract Execution: Chinese Solution Overcomes Multiple Challenges in Overseas Projects

The project construction period spanned complex conditions such as the high-temperature construction season, cross-border standards alignment, cross-border centralized procurement and customs clearance of equipment, and limited work windows during Ramadan. The project team of Sinoma EC Engineering Branch adhered to the principles of “zero safety accidents, zero quality defects and controllable schedule”:

On the design side, it coordinated differences between Chinese and foreign standards and optimized the thermal system and sand/dust prevention scheme;

On the procurement side, it strengthened supervision of long-lead equipment manufacturing and supply chain resilience;

On the site side, it implemented grid-based safety management and modular installation;

On the commissioning side, it prioritized DCS/PLC interlock logic to ensure that the unit “can start up, remain stable and reach full load.”

The owner spoke highly of the Chinese team’s professionalism, contract performance spirit and communication efficiency, and believed that the project provides a replicable model for the low-carbon transformation of the Saudi cement industry.

Strategic Significance: Serving Saudi Vision 2030 and Global Dual Carbon Goals

The project not only fills the gap in ORC technology application by Sinoma Energy Conservation in the Saudi cement industry, but also aligns with the direction of green industry and energy structure transition in Saudi Vision 2030. Based on the 14 MW installed capacity, after commissioning, the project will continuously provide green self-consumption electricity to the cement plant, reduce annual dependence on purchased electricity and CO2 emissions, and achieve a dual improvement in economic and environmental benefits.

Sinoma Energy Conservation Ltd. will continue to provide warranty-period services and long-term technical support. Using this project as a pivot, it will deepen its integrated energy service layout in the Middle East and along the Belt and Road, including industrial energy conservation, waste heat utilization and solar-storage synergy, and promote more “Chinese technology, Chinese equipment and Chinese standards” to go global.