BOO(Build-Own-Operate)
Source: Date:2026.10.10

1.png

Sinoma Energy Conservation International Investment Co., Ltd. contributes capital to establish a project company, which is responsible for power station investment, design, construction, operation and maintenance. The property rights of the power station belong to the investor permanently and are not transferred to the owner. Project payback rely on long-term electricity and heat sales revenue. 

Energy-consuming Enterprise: Provides waste heat resources, land access conditions, and makes a commitment to purchase electricity. 

Sinoma Energy Conservation: Responsible for financing, project full life cycle management, and core technology output. 

Financial Institution: Participates in building the financing system. 

Representative Case: Zambia Industrial Park Waste Heat and Photovoltaic Integration Project 

Total constructing a 36 MWp solar + 7.5 MW WHR hybrid array. 

Meets 70% of the park's electricity demand, with an annual power generation of approximately 110 million kWh. 

Reduces carbon dioxide emissions by 89,500 tons per year, making it the group's first overseas zero-purchase electricity demonstration project.